Three main challenges for Gibela as it readies for R51bn PRASA contract

Gibela CEO Marc Granger
Photo by Duane Daws
Gibela CEO Marc Granger

30th July 2014

By: Irma Venter
Creamer Media Senior Deputy Editor

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Gibela has three main challenges in executing the R51-billion contract to supply the Passenger Rail Agency of South Africa (PRASA) with 600 new trains, says CEO Marc Granger.
 
The first is to complete the design engineering of the X’Trapolis MEtric GAuge (Mega) units Gibela will supply to PRASA’s Metrorail service.
 
The first 20 trains will be built in Brazil, and shipped to South Africa by the end of 2015.
 
This is a relatively easy challenge, says Granger.
 
The second challenge is to start up the factory to produce the remaining 580 trains. Construction at the East Rand site must start in February next year.
 
Gibela, PRASA and the Ekurhuleni municipality must all work together to create the 70 ha industrial park where the trains will be assembled.
 
The third challenge has two parts, adds Granger.
 
Once the Dunnottar facility is available, Gibela will need staff to build the trains.
 
This means Gibela has 18 to 24 months to find and train 1 500 people to build the required rolling stock.
 
Granger aims for the Brazilian assembly project to serve as a training programme for Gibela’s South African employees.
 
The second part of the third challenge is to secure the parts and raw materials required for the trains from a local rolling stock supply chain, which does not, for the most part, exist yet.
 
“This is perhaps the most critical challenge,” says Granger.
 
Gibela, with lead partner Alstom Transport, will create a significant percentage of this supply chain, as part of its black economic-empowerment (BEE) commitments.
 
“Everyone will have to understand what we need, and how they must change and who they must recruit to deliver on these needs,” explains Granger.
 
He is positive that Gibela can deliver on its contractual commitments, as well as on PRASA’s long-term goal of revitalising the South African rail industry.
 
“We will do it. We have done these localisation processes before and we know how to do it. And we have the back-up of Alstom Transport.”
 
R30BN TO BLACK BUSINESS
Gibela aims to source R30-billion in business from black enterprises over the lifespan of the contract, up to 2035.
 
Granger says Gibela has commited to localise 70% of the contract value, with preference given to black-owned businesses.
 
In order to achieve this, the group has completed a detailed analysis of the rolling stock it intends to introduce, to see which parts can be sourced in South Africa.
 
Several companies will have to be developed and nurtured to achieve the quantity and quality demands set by Gibela.
 
One example is Siyahamba Engineering, which already produces coach parts for the local industry.
 
Gibela would like to source its driver cab doors from the 90% black-owned company, but Siyahamba would need to expand and upgrade to deliver the number and quality of doors required.
 
In the end, Siyahamba would probably double in size.
 
“It is important to remember that this is a long, 20-year journey. Everything will not happen on day one,” says Granger.
 
The second leg of the contract’s BEE targets is shareholding.
 
Alstom Transport is the main shareholder in Gibela.
 
PRASA issued a tender that invited entities to participate as shareholders in Gibela, with more than 100 companies participating in the process.
 
PRASA made its decision in 2013, with Ubumbano holding 17% of the 39% shareholding reserved in Gibela for BEE partners.
 
Ubumbano consists of three commercial joint ventures or consortiums, namely Khipunyawo Rail, which has been active in the rail industry for ten years, Elgin-Identity Rail Corporation, which has investment and advisory experience, as well as heavy fabrication expertise, and Community Rail, which is a new entrant into the rail space.
 
Granger says PRASA deliberately did not choose large industrial groups to participate, but small and medium businesses.
 
Ubumbano will need to provide equity to the Gibela consortium.
 
Thirteen per cent of 39% black shareholding is held by an educational trust, a PRASA employee trust and a Gibela employee trust, and the remaining 9% by New Africa Rail, which is a newly created company.
 

Advertisement

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za