https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / South African News RSS ← Back
Africa|Business|Construction|Energy|Engineering|Financial|Gas|PROJECT|Refinery|Refining|Resources|SECURITY|Equipment|Maintenance
Africa|Business|Construction|Energy|Engineering|Financial|Gas|PROJECT|Refinery|Refining|Resources|SECURITY|Equipment|Maintenance
africa|business|construction|energy|engineering|financial|gas|project|refinery|refining|resources|security|equipment|maintenance
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Shrugging off sanctions risk, PetroSA aims to seal GTL refinery investment deal with GazpromBank by April

Close

Embed Video

Shrugging off sanctions risk, PetroSA aims to seal GTL refinery investment deal with GazpromBank by April

The PetroSA GTL refinery in Mossel Bay
The PetroSA GTL refinery in Mossel Bay

11th December 2023

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

South Africa’s PetroSA aims to make a final investment decision (FID) by April on a project designed to support the resumption of production at the mothballed gas-to-liquids (GTL) refinery in Mossel Bay, following receipt of Cabinet’s backing for its controversial selection of Russia’s GazpromBank Africa as the project’s investment partner.

The endorsement was made at a special meeting held on December 8, where Cabinet received an update on progress regarding the reinstatement of the GTL refinery, which has been in care and maintenance since November 2020, following the failure of the $1-billion Project Ikhwezi to replenish the refinery’s dwindling supply of indigenous offshore gas.

Advertisement

Cabinet was also updated on the process followed by the Central Energy Fund, PetroSA’s State-owned holding company, to secure a partner with the “requisite technical and financial resources” to return the refinery to full operation on a risk-sharing basis.

The selection of GazpromBank Africa arose after PetroSA issued a request for proposals in January from potential partners that could offer a turnkey solution, including funding and feedstock security, to refurbish, modify and upgrade the decommissioned facility.

Advertisement

In late November, investigative publication amaBhungane revealed that, while 20 companies submitted bids, the evaluation criteria employed by PetroSA resulted in all but GazpromBank Africa being disqualified. This, despite concerns raised internally about the threat of sanctions, given that the US and the European Union had imposed sanctions on Russia after its invasion of Ukraine in early 2022.

Cabinet spokesperson Khumbudzo Ntshavheni dismissed arguments that the partnership could posed a secondary sanctions risk, noting various exemptions in place, while highlighting that several other countries, including Brics bloc countries, had ongoing energy trade activities with Russian companies.

In a separate briefing, PetroSA acting COO Sesakho Magadla reported that an independent legal opinion had been obtained, which concluded the sanctions risk to be low, owing to the fact that primary sanctions affected companies and individuals from those countries that had imposed the restrictions, while no secondary sanctions had, to date, been imposed on other countries.

Magadla also suggested that “critical energy security”, along with food and medicines, had been exempted from the sanctions.

“This project falls within that description, because it is also critical for South Africa’s energy security,” she asserted.

The tie-up with a Russian company could, however, have implications for PetroSA’s plans to cooperate with TotalEnergies, of France, on the international energy group’s Brulpadda and Luiperd fields, offshore the South African coast.

However, PetroSA indicated that progress had slowed primarily because of pricing issues, with first gas only expected after 2030.

“We cannot be sitting idle and waiting for 2030 while our plant is rotting,” Magadla added.

Ntshavheni noted that the partnership with GazpromBank Africa remained dependent on the FID decision, which would itself be informed by the outcome of a joint bankable business case.

PetroSA is optimistic of reaching FID with GazpromBank Africa on what has been reported to be a R3.7-billion project during the first quarter of the 2024 calendar year.

The company expects to achieve financial close by the end of the second quarter, after which it expects engineering and construction to be implemented over an 18-month period.

PetroSA acting CEO Sandisiwe Ncemane argued that the reinstatement of the project would support security of fuel supply in the Eastern, Northern and Western Cape provinces in a context of declining domestic refining capacity.

The company also argued that reinstating the GTL refinery as soon as possible would help prevent the asset, which it values at $2.85-billion, from further decay.

However, it acknowledged that significant investment would be required to restart production, owing to the fact that some equipment was either obsolete or in poor condition.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za