https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / All News RSS ← Back
Design|Energy|Housing|Mining|Platinum|Renewable Energy|Solar|Storage|Water|Operations
Design|Energy|Housing|Mining|Platinum|Renewable Energy|Solar|Storage|Water|Operations
design|energy|housing|mining|platinum|renewable-energy|solar|storage|water|operations
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

RBPlat studying solar energy, upgrading slimes dams

Close

Embed Video

RBPlat studying solar energy, upgrading slimes dams

RBPlat executive head: operations Neil Carr outlines solar, tailings plans to Mining Weekly Online’s Martin Creamer. Photo: Creamer Media’s Dylan Slater. Video: Creamer Media’s Nicholas Boyd.

5th March 2019

By: Martin Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

JOHANNESBURG (miningweekly.com) – Black-owned and black-managed mining company Royal Bafokeng Platinum (RBPlat) is investigating the use of renewable energy sources and investing in the upgrading of its tailings storage facilities.

The company said in reply to Mining Weekly Online during question time at Tuesday’s presentation of turnaround results that it is doing a study on potential solar energy for Bafokeng Rasimone Platinum Mine (BRPM) – not total load – and for its housing development in Rustenburg. (Also watch attached Creamer Media video.)

Advertisement

“It’s a feasibility study and we should get something on that towards the end of this year,” said RBPlat executive head: operations Neil Carr.

Both of RBPlats tailings dams are being upgraded for further capacity. One of these is the tailings dam serving the BRPM, which was established in the late 1990s, and the other is the Maseve tailings dam, which RBPlat acquired last year. This year’s capital spend on both tailings dams will be R0.3-billion.

Advertisement

Now that BRPM is milling at a rate of 250 000 t a month, the tailings facility has to be expanded to get the rate of rise within recommended levels.

The design of RBPlat’s tailings dams is different to the upstream design of the tailings dam that burst in Brazil last month, killing more than 30 people, and the local topography is flat, as opposed to the mountainous terrain in Brazil.

The initial starter wall is built inwards and not much water is stored in the dams.

“We have very strong operational management of our tailings dams and we have oversight from a third-party consultant on a quarterly basis. We’re evaluating all of that with these recent failures to find out whether we’re doing enough or whether we need to do more to make sure our tailings dams are safe,” Carr explained to Mining Weekly Online.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za