https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / All News RSS ← Back
Construction|Energy|Financial|Gold|Mining|PROJECT|Renewable Energy|Renewable-Energy|Resources|Solar|Storage|Surface|Technology|Environmental|Drilling|Operations
Construction|Energy|Financial|Gold|Mining|PROJECT|Renewable Energy|Renewable-Energy|Resources|Solar|Storage|Surface|Technology|Environmental|Drilling|Operations
construction|energy|financial|gold|mining|project|renewable-energy|renewable-energy-company|resources|solar|storage|surface|technology|environmental|drilling|operations
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Pan African study highlights Mogale Gold's fast payback, low costs, output uplift, ungeared return

Close

Embed Video

Pan African study highlights Mogale Gold's fast payback, low costs, output uplift, ungeared return

Creamer Media photograph.
Photo by Creamer Media
Pan African CEO Cobus Loots.

30th June 2022

By: Martin Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

JOHANNESBURG (miningweekly.com) – Fast payback, low costs, big production uplift, long life, high ungeared return and a lot more is contained in the definitive feasibility study (DFS) on the Mogale Gold tailings storage facilities published by gold mining company Pan African on Thursday.

The Mogale Gold tailings storage facilities form part of Mintails SA’s assets, near Krugersdorp, to the west of Johannesburg.

Advertisement

Payback of the construction capital expenditure of R2.5-billion is estimated to be within 3.5 years after commissioning, with a forecast all-in sustaining cost of $914/oz and an operating cost of R78/t over the initial 13-year life-of-mine.

“As originally anticipated, the Mogale Gold DFS has demonstrated a compelling project, both operationally and financially,” Pan African CEO Cobus Loots commented in a release to Mining Weekly.

Advertisement

The remining of the Mogale gold tailings storage facilities has the potential to add 50 000 oz/y of production over the 13 years, which is equivalent to an increase of 25% on current group production.

The project’s economics involve a pre-tax net present value of more than R1-billion, and an ungeared internal rate of return of 20.1% at a gold price of $1 750/oz.

The project is targeting production within 18 months to 24 months from the start of construction.

Comprising various individual dams, the Mogale gold tailings storage facilities contain a probable mineral reserve of 123.6-million tons of re-mineable material at a head grade of 0.29 g/t for an estimated content of 1.14-million ounces of gold.

Further production upside potential arises from the addition of Mintails SA’s Soweto Cluster resource extending mine life from 13 years to 21 years and further increasing yearly gold production.

The proven technology involves low unit cost hydro mining with low project execution risk at 800 000 t a month through a carbon-in-leach plant, similar to London- and Johannesburg-listed Pan African’s Elikhulu operation, which processes 1.2-million tons a month.

Funding options being considered for the project include offers of debt finance from financial institutions and other third-party financiers.

The project builds on Pan African’s record of bringing surface re-mining operations into production while also ensuring that environmental rehabilitation and socio-economic initiatives for local economic development run concurrently with job creation and skills development in host communities.

Extending the group’s solar renewable energy photovoltaic footprint in line with its decarbonisation strategy and strategic production cost reduction initiatives is also made possible.

Pan African currently operates three surface tailings retreatment operations which assist with environmental remediation.

“We look forward to working with all stakeholders to further progress the project in the months ahead,” added Loots.

Pan African announced that it had entered into conditional sale of shares agreements to acquire the share capital and associated shareholder loans and other claims of Mogale Gold and Mintails SA's Soweto Cluster In November 2020.

Both gold assets are 100% owned by Mintails SA, which was placed into provisional liquidation in 2018.

The deadline for fulfilment of the conditions to conclude the Mintails transaction was extended to August and included the completion of a fatal flaw analysis, prefeasibility study and the DFS.

The fatal flaw analysis was completed on the Mogale Gold tailings storage facilities in July 2021.

Both studies were led by DRA. Further technical work on the Mintails SA's Soweto Cluster is in progress.

To improve mineral resource confidence, a light detection and ranging survey of the entire project area was undertaken to ascertain tonnages, grades verified by twinning 25 of the historical holes, and 82 new boreholes drilled in areas with sparse data.

The combined drilling totalled 2 761 m resulting in 1 877 samples and 187 control samples, resulting in the remodeling of all available resources.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za