https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Statements RSS ← Back
Building|Concrete|Construction|Housing|Innovation|Installation|PROJECT|Sanitation|Storage|Technology|Training|Water|Weir
Building|Concrete|Construction|Housing|Innovation|Installation|PROJECT|Sanitation|Storage|Technology|Training|Water|Weir
building|concrete|construction|housing|innovation|installation|project|sanitation|storage|technology|training|water|Weir
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Minister Majodina commissions world’s highest Piano Key Weir dam in KwaZulu-Natal to improve water supply in eThekwini Metro and surrounds


Close

Embed Video

Minister Majodina commissions world’s highest Piano Key Weir dam in KwaZulu-Natal to improve water supply in eThekwini Metro and surrounds

Water and Sanitation Minister Pemmy Majodina
Water and Sanitation Minister Pemmy Majodina

28th October 2024

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

Water and Sanitation Minister, Ms Pemmy Majodina, has commissioned the world’s highest Piano Key Weir dam, Hazelmere Dam, located in the Mdloti River in KwaZulu- Natal, on Friday, 25 October 2024, with an aim of improving water supply to eThekwini Metro, iLembe and Kwa-Dakuza municipalities in the North Coast. 

The commissioning of the state-of-the-art dam comes after the Department of Water and Sanitation successfully completed a project to raise the dam wall by 7 metres to increase capacity of storage and to augment the water supply to areas such as Verulam, Groutville, Blythedale and Ballito. 

Advertisement

Speaking during a community engagement on Friday, 25 October 2024, Minister Majodina emphasised the important role that municipalities have to play in order to ensure the reticulation of water to households. 

“The Department of Water and Sanitation upgraded the Hazelmere Dam wall to meet the needs of the increasing population in the North Coast as it is our role to ensure bulk water supply. The concerned municipalities should now roll up their sleeves to ensure that water is directed to households,” said Minister Majodina. 

Advertisement

The North Coast of KwaZulu-Natal has experienced rapid growth in recent years, especially in the housing sector which resulted in an increased demand for potable water. The raising of the dam wall will address water challenges in some parts of the three municipalities. 

The project scope of the work entailed the raising of the dam wall by 7m (from 86m to 93.00m) and this included the construction of retrofitting a Piano Key Weir (PKW) onto an existing dam spillway structure, the installation of 83 rock anchors as well as foundation grouting and other minor related works.

Minister Majodina expressed that the Hazelmere Dam forms part of the country’s state-of-the-art dams.

“The Hazelmere Dam can now be measured against world class standards  due the type of spillway selection, technology and innovation used in implementing the project,” said Minister Majodina. 

The dam has an uncontrolled PKW spillway, this was done to ensure that the dam wall withstands extreme concentration of floods of between 6 and 8 hours for the dam catchment area.  

Some of the employed technologies undertaken to upgrade the dam wall included the world’s highest Piano Key Weir, world’s largest anchors were installed to improve stability of the concrete gravity dam wall structure, and the largest capacity post-tensioning stressing jacks were deployed during construction. 

Some of the technologies also employed included the use of innovative data management software for real-time monitoring of anchor performance and 3D digital crack meters.

The upgrading of the wall assisted with the creation of employment opportunities for 187 locals of which 16 were women and 53 were youth. The total number of Small Micro Medium Enterprises (SMME) appointed were 11 with two were women-owned. In addition, successful training of 14 engineers took place during the project, with some subsequently obtaining professional registration, marking a significant achievement in capacity building.

Issued by the Department of Water & Sanitation

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

 

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za