Business|Contractor|Housing|Infrastructure|PROJECT|Projects|Service|Services|Water|Infrastructure
Business|Contractor|Housing|Infrastructure|PROJECT|Projects|Service|Services|Water|Infrastructure
business|contractor|housing|infrastructure|project|projects|service|services|water|infrastructure
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Long wait for dignified housing forces residents to illegally occupy unfinished housing projects

Close

Embed Video

Long wait for dignified housing forces residents to illegally occupy unfinished housing projects

Long wait for dignified housing forces residents to illegally occupy unfinished housing projects

11th December 2023

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

The delays by the Gauteng Department of Human Settlements to complete the River Park housing project in Alexandra have led to frustrated residents illegally occupying the incomplete houses.

For the last six years, no proper bulk infrastructure has been provided to the residents, and there are illegal electricity connections.

Advertisement

The Democratic Alliance (DA) made this discovery during a recent oversight inspection of the housing project. While the actions by the residents are illegal, this once-gain highlights the urgent need by the department to prioritise completing all incomplete housing projects.

During the visit, we also discovered that no services like water and electricity have been provided, as there is a tussle between the City of Johannesburg and the Department of Human Settlements on who needs to provide bulk infrastructure at this site.

Advertisement

The DA will be submitting questions to the MEC for Human Settlements, Lebogang Maile, in the Gauteng Provincial Legislature (GPL) to determine the causes for the delays in completing this project, why the contractor took so long to complete this housing project, and who is responsible for ensuring that bulk service infrastructure is provided to the housing project.

Our residents deserve dignified housing delivered on time.

A DA government will ensure that contractors who receive tenders from the provincial government are held to strict timelines, and where they are unable to deliver, they will be blacklisted from doing business with the government again.

 

Issued by Mervyn Cirota MP - DA Gauteng Shadow MEC for Human Settlements

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

 

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za