/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.
Loadshedding will be suspended at 05:00 on Saturday morning. While the generation capacity constraints persist, the suspension of loadshedding is possible due to the anticipated lower weekend demand, as well as adequate levels of emergency generation reserves. Eskom will publish a further update on Sunday afternoon, or as soon as there are any significant changes.
Since yesterday afternoon a generation unit each at Camden, Grootvlei, Hendrina, Kendal, Kriel, Majuba and Tutuka power stations have returned to service.
A generating unit at Duvha Power Station was taken offline for repairs.
We currently have 5 512MW on planned maintenance, while another 13 484MW of capacity is unavailable due to breakdowns.
Loadshedding is implemented only as a last resort in view of the shortage of generation capacity and the need to attend to breakdowns.
Issued by Eskom
EMAIL THIS ARTICLE SAVE THIS ARTICLE ARTICLE ENQUIRY
To subscribe email subscriptions@creamermedia.co.za or click here