JDA restarts construction of roads and stormwater infrastructure in Bramfischerville


Close

Embed Video

JDA restarts construction of roads and stormwater infrastructure in Bramfischerville

3rd November 2022

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

/ MEDIA STATEMENT / The content on this page is not written by Polity.org.za, but is supplied by third parties. This content does not constitute news reporting by Polity.org.za.

The Joburg Development Agency (JDA) has restarted the construction of roads and stormwater infrastructure in Bramfischerville Ext 12, Soweto. 

The implementation of the project has undergone many challenges. The two previous contractors who started the work had their contracts terminated due to poor performance, which delayed completion of the project.

Advertisement

Bramfischerville is one of the focus areas for the City of Johannesburg in terms of addressing service delivery in marginalised areas across the City. 

The construction of roads and stormwater infrastructure in the area is back on track after the JDA appointed DKBP Construction, which will complete the undone scope of works. The overall scope of works to be undertaken includes: 

Advertisement
  • Earthworks, layer works and paving (asphalt and pavers);
  • Construction of sidewalks,
  • Replacing damaged kerbs
  • Construction of new stormwater infrastructure and associated works.
  • Protection of services.
  • Remedial work to existing stormwater services and,
  • Construction of signage and markings,
  • Construction of attenuation dam and fencing.

The JDA aims to create short-term job opportunities and employ community-based emerging contractors. To date, 35 job opportunities and five community-based emerging contractors are part of the project.

 

The JDA’s Executive Manager: Project Implementation, Siyabonga Genu, said: “This project has had various challenges in the past that have delayed its implementation, but we are happy that the JDA made sure this project is back on track.”

“The safety of the public and all affected parties remains of the utmost importance to us. We apologise for the inconvenience caused,” Siyabonga said.

 

Issued by the City of Johannesburg

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

 

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za