https://www.polity.org.za
Deepening Democracy through Access to Information
Home / News / All News RSS ← Back
Africa|Energy|Engineering|engineering news|Eskom|Generators|Power|PROJECT|Projects|Solar|System
Africa|Energy|Engineering|engineering news|Eskom|Generators|Power|PROJECT|Projects|Solar|System
africa|energy|engineering|engineering-news|eskom|generators|power|project|projects|solar|system
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

Eskom’s new grid queuing rules governed by ‘first ready, first served’ approach

Close

Embed Video

1

Eskom’s new grid queuing rules governed by ‘first ready, first served’ approach

Eskom power lines and substation
Photo by Creamer Media

20th June 2023

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

State-owned electricity utility Eskom is preparing to issue updated grid queuing rules that will outline how it plans to manage scarce grid connection capacity in a way that avoids “hogging” of capacity and ensures that only “shovel-ready” project are allocated capacity.

The new approach is contained in what Eskom terms its Interim Grid Capacity Allocation Rules (IGCAR) document, which outlines a shift from the ‘first come, first served’ framework that has hitherto been implemented to one based on ‘first ready, first served’.

Advertisement

The absence of a queuing system came to the fore during the sixth bid window of the country’s public renewables procurement programme when none of the 23 onshore wind projects that bid for a 3 200 MW allocation were selected as preferred bids, owing to claims of grid over-subscription in the Western, Eastern and Northern Cape provinces.

Eskom tells Engineering News that the rules under the IGCAR are “aimed at ensuring that as many generators are connected to the grid as soon as possible and also ensuring that there is no capacity hogging”.

Advertisement

The IGCAR has been developed following consultation with the industry and, while they do not require any approval by the National Energy Regulator of South Africa, given that Section 21 of the Electricity Regulation Act grants Eskom power over the rules, the utility will nevertheless seek to have the rules adopted and approved by the regulator.

In addition, Eskom intends hosting a briefing session with industry in the coming two weeks to clarify how it intends managing the IGCAR.

Eskom has also communicated with the industry that it will resume with processing budget quotes (BQs) for grid access in the Cape region once the IGCAR process has been finalised.

Having also been criticised previously for the length of time it was taking its Grid Access Unit to issue BQs, Eskom reports that it is in the process of ensuring that timeframes can be reduced.

“On average in the last 12 months, it has taken eight months to issue a BQ due to issues both internal to Eskom and in the industry,” Eskom tells Engineering News.

The utility confirms that its Grid Access Unit currently has 28 staff members, but stresses that the bulk of the technical work is done by the various technical experts in the distribution and transmission divisions.

“The goal is to issue BQs within six months and the introduction of the IGCAR and other initiatives will result in improved delivery times,” Eskom states.

“There are currently 45 BQs that have been issued between 1 April 2021 to 30 November 2022 which have been delayed for various reasons with a total capacity of 4 717 MW.”

The importance of having queuing rules that are supportive of shovel-ready projects has been amplified by the result of a recent survey showing that there is a 66 GW pipeline of wind and solar projects at various stages of development, including about 18 GW that could be considered ready to proceed.

There have also been intensifying calls for a clarification of the rules in light of the fact that the market is no longer dominated by a single public procurement programme, following the removal of the licensing threshold for embedded generation projects.

Operation Vulindlela reports that this reform, together with a streamlining of project approvals means that projects are theoretically able to add capacity to the grid more quickly and has resulted in an embedded generation project pipeline of 108 projects  with a combined capacity of just over 10 GW.

During a recent presentation to the Presidential Climate Commission, the Presidency’s Rudi Dicks, who oversees Operation Vulindlela, confirmed that Eskom was revising its grid capacity allocation principles with the aim of allocating available capacity to projects that are ready to proceed.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za