Eskom warns of possible blackouts after belt feeding coal to Medupi station snaps

Close

Embed Video

2

Eskom warns of possible blackouts after belt feeding coal to Medupi station snaps

 Eskom warns of possible blackouts after belt feeding coal to Medupi station snaps

10th September 2020

By: African News Agency

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

South African power supplier Eskom warned on Thursday it might be forced to resort to rolling blackouts again to ease pressure on the shaky national grid after a conveyor belt feeding coal into its Medupi generation units failed.

The State-owned utility, which provides some 95 percent of the country’s electricity, has effected loadshedding intermittently for more than a decade as its ageing infrastructure has struggled to generate enough to meet demand.

Advertisement

The company is also beset with financial problems blamed on years of mismanagement by executives who have since left.

On Thursday it said the incident at its Medupi power station meant that the four generation units in service were not able to take in the requisite amount of coal to generate electricity.

Advertisement

“This puts further strain on Eskom’s ability to fully supply electricity over the next 24 hours,” it said.

“While Eskom teams are working round the clock to repair the conveyor belt, which is expected to take the better part of the day, any further breakdown elsewhere in the generation fleet, would necessitate the implementation of Stage 2 loadshedding at short notice.”

Stage 2 loadshedding entails suppressing 2 000 megawatts of electricity demand at any given time to avoid overwhelming the grid and making it trip.

“Eskom will continue to communicate should there be any further changes as the system remains unreliable and vulnerable,” the company said.

Last week group chief executive André de Ruyter suspended the managers at Eskom’s Tutuka and Kendal stations pending disciplinary inquiries after breakdowns which forced the utility to ramp up rolling blackouts earlier in the week.

The state firm said a previous culture of weak consequence management would no longer be the norm and would no longer be tolerated at Eskom.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za