Eskom|South Africa|B-BBEE|Electricity Wheeling|Energy Transition|Loadshedding|Business Leadership South Africa|Development Bank Of Southern Africa|Eskom Restructuring Task Team|Infrastructure Finance And Implementation Support Agency|National Transmission Company South Africa|National Treasury|Busisiwe Mavuso|Cyril Ramaphosa|Mteto Nyati
||||
eskom|south-africa|b-bbee|electricity-wheeling|energy-transition|loadshedding|business-leadership-south-africa-organization|development-bank-of-southern-africa-organization|eskom-restructuring-task-team|infrastructure-finance-and-implementation-support-agency|national-transmission-company-south-africa-organization|national-treasury|busisiwe-mavuso|cyril-ramaphosa|mteto-nyati
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

End-2027 timeline outlined for independent Transmission System Operator


Close

End-2027 timeline outlined for independent Transmission System Operator

Should you have feedback on this article, please complete the fields below.

Please indicate if your feedback is in the form of a letter to the editor that you wish to have published. If so, please be aware that we require that you keep your feedback to below 300 words and we will consider its publication online or in Creamer Media’s print publications, at Creamer Media’s discretion.

We also welcome factual corrections and tip-offs and will protect the identity of our sources, please indicate if this is your wish in your feedback below.


Close

Embed Video

End-2027 timeline outlined for independent Transmission System Operator

End-2027 timeline outlined for independent Transmission System Operator

7th September 2026

By: Terence Creamer
Creamer Media Editor

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

The request for proposals (RFP) issued for the appointment of a transaction adviser to support the establishment of a fully independent Transmission System Operator (TSO) confirms that the adviser will not re-evaluate the policy decision to establish the TSO as a State-owned entity outside of Eskom and with ownership and control of the transmission network.

This policy decision was reaffirmed as “feasible and in line with international best practice” in a Phase I report by the Eskom Restructuring Task Team (ERTT), and was subsequently endorsed by President Cyril Ramaphosa at the end of July.

Advertisement

In February, Ramaphosa set up the ERTT to develop a detailed proposal and implementation plan for the creation of such an entity, contradicting an earlier Eskom plan for the TSO to be set up without the transmission assets and for those to continue to be held by an Eskom Holdings subsidiary.

The RFP, which is now available, states that the assignment is confined to advising on an optimal transaction structure and assisting with executing the transaction in accordance with the approved roadmap.

Advertisement

This, too, is in line with Phase II, during which the ERTT is expected to deliver a detailed implementation plan with timeframes for completing the restructuring “in the manner proposed”.

The RFP, which includes various time-defined milestones for the adviser, states that the establishment of the TSO should be completed by December 31, 2027.

Issued for the National Treasury by the Infrastructure Finance and Implementation Support Agency, which is hosted by the Development Bank of Southern Africa, the RFP has a submission deadline of September 28, with a compulsory briefing session for prospective bidders to be held on September 14.

Should a bidder meet the various qualifying criteria outlined in the document, including proof of at least two assignments with a minimum transaction value or asset value of R50-billion where the company successfully led or advised on corporate restructuring, the submission will be evaluated using an 80/20 points system, with 80 points related to price and 20 points for broad-based black economic empowerment.

LENDER ENGAGEMENT

The appointed adviser is expected to provide integrated financial, legal and tax advice to the National Treasury on the transaction, as well as on a lender-engagement strategy.

“The proposed restructuring is likely to trigger consent requirements across a substantial portion of Eskom’s debt portfolio, so a strategy for engaging with and securing the required consents from lenders must also be developed,” the document reads.

The project scope, thus, specifically requires the transaction adviser to advise on the development of a strategy for and facilitate engagements with rating agencies and lenders to secure the “consents, waivers, amendments or approvals” required to close the transaction.

The adviser is also expected to facilitate engagements with potential lenders to secure cost-effective financing for Eskom, the TSO and the fiscus to finance the transaction and future capital investment.

It is also expected to confirm the opening capital structure of each entity, as well as the allocation of existing debt and government guarantees, while advising on the issues to be addressed in the execution of the transaction, including the transfer of staff, assets, and contracts.

Besides a step-by-step implementation plan for the legal separation of the National Transmission Company South Africa from Eskom, a dispute-resolution mechanism between stakeholders during the course of the project should also be recommended.

The document reaffirms that this should be performed while meeting several core principles, from maintaining energy security and ensuring that Eskom is no worse off than its current financial position following the restructuring, to positioning the TSO to be able to raise the funding required for investment in infrastructure in line with the Transmission Development Plan.

By excluding from its scope any revisiting of government policy in relation to the TSO, the RFP appears to draw a line under a period of uncertainty about how the unbundling process would unfold, particularly given recent statements by Eskom chairperson Mteto Nyati that questioned the immediate transfer of the utility’s grid assets to the TSO.

The remarks drew strong criticism from Business Leadership South Africa (BLSA) and even a rebuke from the Presidency.

Nyati has since met with both Ramaphosa and BLSA, after which Nyati endorsed government’s commitment to establish a fully independent TSO with ownership and control of the transmission assets as “the right policy”, while still raising execution risks.

In her weekly newsletter, BLSA CEO Busisiwe Mavuso has welcomed the release of the RFP and its “ambitious” timetable, indicating that the transaction should be concluded in the next 18 months.

“It will be highly positive if this timetable can be achieved,” Mavuso writes.

EMAIL THIS ARTICLE      SAVE THIS ARTICLE      ARTICLE ENQUIRY      FEEDBACK

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here


About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za