https://www.polity.org.za
Deepening Democracy through Access to Information
Home / Opinion / Other Opinions RSS ← Back
Africa|Building|Coal|Components|Efficiency|Energy|Eskom|Financial|Gas|Industrial|Logistics|Nuclear|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|Resources|Road|SECURITY|Solar|Storage|Sustainable|Technology|Maintenance|Operations
Africa|Building|Coal|Components|Efficiency|Energy|Eskom|Financial|Gas|Industrial|Logistics|Nuclear|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|Resources|Road|SECURITY|Solar|Storage|Sustainable|Technology|Maintenance|Operations
africa|building|coal|components|efficiency|energy|eskom|financial|gas|industrial|logistics|nuclear|power|project|projects|renewable-energy|renewable-energy-company|resources|road|security|solar|storage|sustainable|technology|maintenance|operations
Close

Email this article

separate emails by commas, maximum limit of 4 addresses

Sponsored by

Close

Article Enquiry

2024 - Once again electricity

Close

Embed Video

2024 - Once again electricity

Opinions

22nd January 2024

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Font size: -+

Over the holiday period there were several important developments regarding the major issue facing the country, electricity.

By far the most important was the release of the long-term electricity plan, the Integrated Resource Plan 2023 or IRP 23. This is a still a draft. After public comments, it will be gazetted to replace IRP 2019. Even as a draft, it is a wholly unsatisfactory document that lets the country down in a crucial area of development. We will discuss this below.

Advertisement

Government also announced three bid windows for 5 000 MW of renewable energy, 2 000 MW of gas with another one for 1 000 MW of gas specifically in Nelson Mandela Bay to come later in the year and 615 MW of battery storage.

A request for proposals (not a bid window) for 2 500 MW of nuclear power is also envisaged for 2024. A nuclear power station takes 10 – 15 years to develop. This will not make any difference between now and 2030 and we will revert to the issue once the proposals are in and we know what is at stake.

Advertisement

Another important piece of information came from energy analyst, Chris Yelland. Based on Eskom data, he calculates that the utility’s energy availability factor (EAF) declined from 58% in 2022 to 54.7% in 2023. This is a stark summary of relentless decline at Eskom and makes a mockery of EAF targets of 65% and 70% set at various stages by management and politicians.

IRP 23: Visionless and without urgency

The IRP comes to the bleak conclusion that even with new capacity (including 3 000 MW gas from Eskom), loadshedding can be expected to continue into 2027. Publishing a ‘plan’ that includes loadshedding for another four years can only be called negligent planning. Common sense dictates that such a plan must set out a path towards plugging the supply deficit and eliminating loadshedding.

The prognosis of loadshedding continuing until 2027 is premised on a very realistic EAF of 49% to 51%. The only scenario in IRP 23 where loadshedding is overcome, is with an EAF of 66% to 69%. Given the trend in Eskom EAF that is clearly wishful thinking.

Relief from loadshedding can only come from new investments. This is where IRP 23 really lets the country down.

There is general agreement that South Africa needs 60 000 MW of new capacity over ten years – about 6 000 MW per year. The Presidential Climate Commission, for example, recommended 50 000 to 60 000 MW of new renewable capacity over ten years, plus 3 000 to 5 000 MW of new gas. But for the seven years to 2030 IRP 23 only provides for a total of 28 000 MW to be added, leaving a shortfall of 22 000 to 32 000 MW. For a country in an electricity crisis, this is wholly visionless and without urgency.

Inexplicably, IRP 23 does not include the 5 000 MW renewables from Bid Window 7 released in December. It also does not include 5 000 MW from a future Bid Window 8, which the minister still has authority to issue. That will cut the deficit by 10 000 MW.

IRP 23 also states that more solar and wind power from the private sector is expected to be connected after 2027 but does not bring any numbers into the plan. This week it was NERSA revealed that in 2023 nearly 4 500 MW new capacity were installed across 392 plants. A log we keep of private projects announced in the media comes to about 11 000 MW to be added in the next 3 to 4 years. Incomplete as the log may be, one cannot just ignore the private sector contribution.

IRP 23 - renewables, gas and coal

Of the 28 000 MW of new capacity over the next 7 years which the IRP foresees, 69% will be renewables (wind & solar), 21% gas, 5% dispatchable capacity (essentially storage capacity in whatever technology) and 5% coal.

 The 5% for coal refers to the last two units at Kusile and Medupi that will come online during the IRP period. Essentially there is no new coal. Two 750 MW coal plants provided for in IRP 2019, which the minister never activated, do not re-appear in IRP 23. The IRP notes that the GeoScience Council and World Bank are undertaking a study at a site in Leandra in Mpumalanga to explore clean coal technologies. Should such technologies indeed be developed, coal could feature again in the period after 2030.

Although it is in IRP 23, I excluded from the 21% gas calculation 1 200 MW of gas from Karpowership. The day after the IRP was released, Eskom announced that it had cancelled the transmission grid capacity reserved for Karpowership and two other providers as they could not reach financial closure for their projects by 31 December. Hopefully this is the end of the inappropriate Karpowership deals, even though the IRP draft still includes it.

Another example of reality outstripping the plan, is the provision for 3 000 MW gas from Eskom. Industry insiders put the cost of that project at R30 billion and more. However, the R254-billion Treasury bailout of Eskom prohibits any further capex apart from essential maintenance. It also prohibits further debt taken on by Eskom. It is unclear how the drafters of IRP 23 think the Eskom project will materialise.

As the IRP now stands it is already outdated on this 4 200 MW of gas. Presumably, that would be fixed in the final draft.

Missed opportunity to spur re-industrialisation

At 69% of new capacity, renewables dominate the bid windows. Sadly, that is not enough.

Quite apart from the fact that 32 000 more MWs are needed, the miserly allocation for renewables undermines industrial development.

In 2024, for example, IRP 23 envisions only 1 000 MW of solar renewables to be installed; in 2026 only 1 040 MW; in between in 2025 there is a spike to 3 000 MW. With such a limited and fluctuating uptake, how can industrialisation and localisation of renewable power components take place? If we play our cards right, green energy can play a huge role in re-industrialising the country. The opportunity is right in front of us, but who will build a factory to produce solar panels or wind components if uptake is going to be so limited and fluctuating? We learnt that lesson when Brian Molefe suspended renewable energy contracts in 2016 and a solar panel factory in KZN had to close down.

Now what?

There is one big difference between IRP 2019 and IRP 2023, and this is the regulatory context.

The changes announced by President Cyril Ramaphosa in 2021 and 2022 created a liberated electricity market where private players can do their own thing, irrespective of what the minister publishes in an IRP. Over the last two years we have seen private players, from households to big corporates, using this freedom to create their own supply. Traders and energy exchanges are also emerging to buy and sell power, further expanding supply and consumption.

Over the last year many companies have started embracing renewable power, partly to beat loadshedding but also to move towards being carbon neutral. Anglo American SA, for example, are aiming for 5 000 MW of renewable power by 2030, to be carbon neutral by 2040. 5 000 MW is as much as a whole government bid window. Similar stories are unfolding at many other companies. Even the country’s biggest coal producer, Exxaro, will not invest in more coal assets and are rather hunting for renewable assets. Earth & Wire, a private sector ‘utility’, has already signed agreements to provide many thousands of MWs to various buyers. The genie has left the bottle.

Reflexivity, the theory that an action carries in it a counteraction, is also at work here. The more IRP 23 states that loadshedding will continue to 2027, and the more it works with unrealistic gas assumptions, the more people will note the failures and make their own arrangements.

It would be better if there was one national plan that mobilised the public and private sector to play their respective roles to eliminate loadshedding and undertake the long-term development of the energy sector. But IRP 23 is not that.

So, we will have to rely on private sector initiatives to get us over the line. This is happening.

Transmission capacity

The transmission grid is still a concern, but fortunately also a priority, both in terms of money and attention.

National Treasury has signed two agreements with European lenders for concessional loans to be used for transmission expansion. The terms of government’s bail-out of Eskom for R254-billion are creating a bottleneck now, because of the prohibition on capex programmes mentioned above. That of course impacts investment in transmission. The new National Transmission Company, for whom a new board was announced this week, will be fully operational from 1 April, and the European money will probably go to that company to proceed with expanding transmission.

Eskom Transmission currently envisions that 1 675 km of new lines will be built by 2027 and 12 500 km thereafter. Power Operations & Leadership Association of Southern Africa (Polasa), an industry organisation, has called this a ‘famine and feast’ scenario and argued for some of the projects to be brought forward. Minister of Electricity, Kgosientsho Ramokgopa, who was recently given responsibility for the transmission network, acknowledged the problem in his first news conference of the year. He set a goal of building 6 000 km over 3 years and said he has a mandate to look for private capital to co-finance that.

Economic impact

Due to electricity and logistics constraints, 2024 will again be a tough year economically. Nobody is expecting the economy to grow at the population growth rate of 1.8%. This means that 2024 will be the 11th year in which the economy grew more slowly than the population and the country is getting poorer. We already have a decade of declining per-capita incomes behind us.

That of course impacts unemployment, poverty, the ability of government to collect taxes, having sufficient resources for development. It affects everything. Electricity must be resolved, and logistics cleared. Only then can the country again enjoy a rise in per capita incomes.

So what?

  • The further decline in Eskom’s EAF (Electricity Availability Factor) to less than 55% for 2023 underlines the futility of wishing for higher efficiency numbers to deal with loadshedding. It is truly a case of ‘hope over experience’ - particularly with power stations that are getting older with each passing year.
  • The only sustainable way to energy security is massive investment in new capacity. The country needs between 50 000 and 60 000 MW of new capacity by 2032. IRP 23 only envisages 28 000 MW and that includes a dubious gas project by Eskom. It leaves a huge supply gap.
  • Fortunately, regulatory reform since 2021 has opened the way for private sector involvement in electricity. loadshedding, rising tariffs and ESG concerns are spurring that involvement on. This should help to plug the supply deficit.
  • Getting out of the electricity crisis is a big opportunity for South Africa to stimulate investment, growth, and re-industrialisation. IRP 23 does not seize this opportunity.
  • The Just Energy Transition (JET) plan is a much better road map for the country’s evolving energy sector. We will monitor how that is implemented.

Written by JP Landman, Political & Trend Analyst

EMAIL THIS ARTICLE      SAVE THIS ARTICLE ARTICLE ENQUIRY

To subscribe email subscriptions@creamermedia.co.za or click here
To advertise email advertising@creamermedia.co.za or click here

Comment Guidelines

About

Polity.org.za is a product of Creamer Media.
www.creamermedia.co.za

Other Creamer Media Products include:
Engineering News
Mining Weekly
Research Channel Africa

Read more

Subscriptions

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

View store

Advertise

Advertising on Polity.org.za is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za

View options

Email Registration Success

Thank you, you have successfully subscribed to one or more of Creamer Media’s email newsletters. You should start receiving the email newsletters in due course.

Our email newsletters may land in your junk or spam folder. To prevent this, kindly add newsletters@creamermedia.co.za to your address book or safe sender list. If you experience any issues with the receipt of our email newsletters, please email subscriptions@creamermedia.co.za